Line No. | Header Row | Instruction | |
1 |
|
SAFETY
Gloves and ear plugs are to be worn throughout this operation.

Be careful of pinch points. Keep fingers clear at all times when the machine is operating.
| Edit Delete |
2 |
|
SETUP & PREPARATION
- Ensure the machine and tooling setup is complete.
- Daily Maintenance
- Correct tool is selected for the process
- Ensure tool height is correct after setting. Tool height must measure 119.60 mm - Verify using slip gauges. Refer below pic:

Ensure the correct wire has been issued by validating GRN buff tag against the route card.
On the production system log the time as "Setting."
Set press & tool height accordingly and prepare a First-Off sample.
Once the first-off is correct, on the production system end the "Setting"downtime and enter the job number and operation to start the job.
Enter the first-off inspection results in the production system.
| Edit Delete |
3 |
|
QUALITY CHECKS
The following checks should be performed:
- Do not force the part into the checking fixture.
- Wires should follow the profile of the checking fixture
Examples
Good


Rejects


| Edit Delete |
4 |
|
QUALITY INSPECTION
- The Last-off from the previous batch is to be compared to the current batch First-off. Last-off is to be placed in the production run.
- Complete a First-off before comencing with production, record on system Inspection Number "20443".
- First-off sample to be tagged and remain with the checking fixture.
- Conduct in-process inspections every hour and record on system Inspection Number "20444".
- At the end of the batch, last part is to be tagged and kept with the checking fixture. First-off is to be placed in the production batch and record on system Inspection Number "20445".
| Edit Delete |
5 |
|
REJECTS
- All reject parts are to be placed immediatley in the red reject bins provided.
- All rejects should be logged on the system hourly.
Scrap / Reject bins are to be emptied at the end of end job or at the end of shift if the job is running at the end of shift
|
 |
|
| Edit Delete |
6 |
|
Once the job has been logged on the system, you will be able to see the production figures and targets including
- The Total Qty made against the job
- The quantity prodcued on the shift (day),
- The Std Time and the number of Parts required to be made per hour.
The picture to the left provides and example.
|
 |
Production figures are to be logged on the system every hour.
|
| Edit Delete |