Line No. | Header Row | Instruction | |
1 |
|
SAFETY
Gloves and ear plugs are to be worn throughout this operation.

Be careful of pinch points. Keep fingers clear at all times when the machine is operating.
- Keep hands and clothing away from moving parts at all times.

| Edit Delete |
2 |
|
.PUNCHING TOOL SET UP
.Tool height when opened is 74.00 mm on both sides(use gauge blocks/ slip gauges to verify. Refer pictures below:

.The left and right side must be level and measure 74.00 mm.
.The Gibb Height is 330mm. Measured from the base of machine. Refer pictures below.

SETUP & PREPARATION
- Ensure the correct parts are accompanied with a BIS card.
- Daily Maintenance is completed.
- Stamping Tool is correct and not worn.
- Tool is secure on press.
- Ensure to test the press to prvent it from jamming by not putting a part in the tool and stamped it.
- Check pressure levels - Pressure should be set between 7 - 8 Bars.
On the production system log the time as "Setting."
Prepare a First-Off sample and ensure that it is verified by Quality.
Once the first-off is correct, on the production system end the "Setting"downtime and enter the job number and operation to start the job.
Enter the first-off inspection results in the production system.
| Edit Delete |
3 |
|
QUALITY CHECKS
The following checks should be performed:
- Do not force the part into the checking fixture.
- The legs should be parallel and flat.
- When placed on a flat surface the legs should not rock.
- After stamping the part legs shall be flat or have a 0.40 mm MAX gap. Use a 0.5mm feeler gauge to check the gap. The 0.5mm gauge should not fit through.
- When checking part for flatness ensure the flat side is on the bottom.
- Stamping thickness of the legs is from 4.50 mm - 4.70 mm.
- Ensure the part is corrrectly placed in the tool before stamping.
Examples

NG gap too big after stamping. 0.50 mm feeler gauge is fitting through.
OK - part is flat, the 0.50 mm feeler gauge does not fit through.


|
|
| Edit Delete |
4 |
|
QUALITY INSPECTION
- The Last-off from the previous batch is to be compared to the current batch First-off. Last-off is to be placed in the production run.
- Complete a First-off before comencing with production, record on system Inspection Number "8279" "Assembled Frame First-off".
- First-off sample to be tagged and remain with the checking fixture.
- Conduct in-process inspections every hour and record on system Inspection Number "8280" "Assembled Frame Inprocess"
- At the end of the batch, last part is to be tagged and kept with the checking fixture. First-off is to be placed in the production batch and record on system Inspection Number "10371"
|
| Edit Delete |
5 |
|
REJECTS
- All reject parts are to be placed immediatley in the red reject bins provided.
- All rejects should be logged on the system hourly.
Scrap / Reject bins are to be emptied at the end of end job or at the end of shift if the job is running at the end of shift
|
 |
| Edit Delete |
6 |
|
PERFORMANCE TARGETS
Once the job has been logged on the system, you will be able to see the production figures and targets including
- The Total Qty made against the job
- The quantity prodcued on the shift (day),
- The Std Time and the number of Parts required to be made per hour.
The picture to the left provides and example.
|
 |
Production figures are to be logged on the system every hour.
|
| Edit Delete |