PROCESS FLOW | NO | NAME | WORK ELEMENT | CHECK ITEM | RANK | PROCESS CRITERION | INSPECTION METHOD | INSPECTION PLAN | FREQUENCY | Inspection No.(s) | Work Instructions | RESP | CHECK SHEET | CONFIRM'N LEVEL | REACTION PLAN | |
| 1 | Receiving raw material - Stores Personnel | Receiving | Raw material |
| Check for correct quantity delivered, type, Diameter. Check for COA | Visual verification and verification as per order | Delivery note and order | Every batch |
|
1090
|
| Goods receive note book / delivery note |
| Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D |
|
| 2 | Move raw material to incoming inspection area | Transport | Raw material |
| Store material properly in bays | Visual verification | As per FIFO system | Every batch |
|
|
| Visual inspection |
| If difficulty occurs in storing raw material properly inform Stores Coordinator |
|
| 3 | Raw material incoming inspection by QA Personnel | Inspection | Raw material |
SC
| Correct Ø - 6.50 mm ± 0.06 mm. Correct type - Spring black wire. Tensile range 1380mpa - 1550mpa. No rusty wire. No score marks. No excessive drawing soap | Visual inspection and measure with a Micrometer | As per online incoming raw material inspection plan | Every consignment |
6178
|
1120
|
| Goods receive notebook/ Buff tag and record findings on system |
| Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator |
|
| 4 | Move wire to storage area for safe stacking | Transport | Raw material |
| Safe stacking of wire coils onto racks as per allocated areas and FIFO system | Visual verification | As per FIFO system | On receiving |
|
|
| Identification tags |
| Any difficulty experienced during this activity report to Stores Coordinator |
|
| 5 | Issue raw material to Production Personnel | Issuing | Raw material |
| Correct wire to be issued as per route card | Verification against buff tag | Every coil issued to production. | Every job as per request |
|
1080
|
| Route card |
| Should the incorrect wire be issued to production stop process, correct and inform Stores Manager |
|
| 6 | Straighten wire and cut to length | Straighten and cut to lengths | Product |
SC
| Correct cut length - 550.00 mm ±1.00 mm | Visual inspection and tape measure | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
|
| Record on inspection system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor |
|
| 7 | Move straight cut wire to wire bender | Transport | Product |
| Safe transportation of wires | Visual verification | N/A | Every order |
|
|
| N/A |
| Any difficulty experienced during this activity stop the process and report to Supervisor |
|
| 8 | Form bend 1 on hand bender | Forming | Product |
SC
| Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issues | Visual inspection and checking fixture | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
1176
|
| Record on inspection system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervison |
|
| 9 | Form bend 2 on hand bender | Forming | Product |
SC
| Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issues | Visual inspection and checking fixture | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
1176
|
| Record on inspection system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor |
|
| 10 | Form radius | Forming | Product |
SC
| Component shall conform to checking fixture, component to fit profile correctly on fixture to prevent fitment issues | Visual inspection and checking fixture | As per work instruction | First-off at start of production. In-process 9 parts every hour and last-off |
|
1176
|
| Record on inspection system |
| Should the first-off sample fail - stop process - reset machine and redo first-off. Any further non-conformance report to Supervisor |
|
| 11 | LTHT of torsion bar | LTHT | Product |
| 240 °C for 30 mins | Visual verification. Record on heat treatment log sheet (QD:52) | Visual inspection temperature. | Every batch |
|
|
| Record oven temperature on QD:52 |
| Any difficulty experienced during this activity stop the process and report to supervisor. |
|
| 12 | Final inspection of torsion bar | Inspection | Completed products |
| Component shall conform to customer/ drawing requirements. Bend 1 length: 30.00 mm ±2.00 mm, bend 3 length: 63.00 mm ±2.00 mm, Correct overall length: 375.00 mm ±2.00 mm - Refer CAR 52420. No burrs/ sharp edges & correct fitment on checking fixture | Checking fixture, vernier and visual verification | As per work instruction | Every batch |
103621036310364
|
1176
|
| Record on inspection system |
| Should the inspection requirements not be correct, stop the process and inform the Supervisor |
|
| 13 | Transport completed components to stores. | Transport | Completed products |
| Safe loading and transporting of components. | Visual inspection. | As per job order | Every order |
|
|
| N/A |
| Should difficulty occur during transport inform Supervisor |
|
| 14 | Receipt of components | Receipting | Completed parts |
| Correct quantity to be entered on to the stock system | Visual verification against F.A card | Cross off the F/A card to indicate it has been received on the system. | Every batch |
|
1094
|
| F.A Card |
| Any discrepancies shall be reported to the Stores Manager |
|
| 15 | Despatching of components. | Transport | Completed products |
| Safe handling during this activity. | Verification of quantities as per sales order and delivery note. | As per job order | Every order |
|
1101
|
| Delivery note / invoice |
| Any difficulty experienced during this activity report to Stores Coordinator |
|
| 16 | Internal product audit. | Inspection | Completed products |
| As per drawing and audit requirements. | Competent Q.A personnel conducting inspections. | 1 complete product | As per schedule |
|
1180
|
| Audit sheet |
| Should the audit fail, the Production manager shall be informed immediately. |
|